Mar 21: 8Project Name: Greenfield 2G BIO Ethanol Refinery
8Project Cost: Rs 700 Crore
8Project Description: An owner is planning to construct an ethanol plant based on the DBT-ICT 2G Ethanol technology developed indigenously to produce 100 KL fuel-grade ethanol per day, primarily from biomass and will use approximately 1 MTPD of biomass per day. At present, a private company is hired as PMC contractor.
8Project Event: RFQ for the DFR consultant is expected by May 2018.
8Expenditure Approval : Q3:2017
8RFQ Date: May/2018
8Release Date: Jun/2018
8Start Date : Q4:2018
8Completion Date : Q4:2021
Click here for more details.

8Project Name: Greenfield Natural Gas Pipeline Project
8Project Cost: Rs 900 Crore
8Project Description: An owner is planning to install a Greenfield Natural Gas transportation pipeline.
8Project Event: RFQ For PMC contractor is to be expected by May 2018.
8Expenditure Approval : Q4:2016
8RFQ Date: May/2018
8Release Date: Jun/2018
8Start Date : Q4:2018
8Completion Date : Q4:2020