All content in this website is sourced legitimately

Page No: 1
Software updates: Upstream projects
Mar 15: Key contacts, dedicated analyst support, search fields involving dozens of project, a backend CRM and plant parameters are among the benefits that our project monitoring software offers. We carry as many as 10 leads everyday encompassing the entire oil & gas sector. No other site provides this amount of detailing in India. A large team of dedicated engineers are at work to fulfill the client's quest for a deal.
8
Project Name: Development Drilling Project
8Project Cost: Rs 4000 Crore.
8Project Description: Promoter has planned development drilling of 100 oil wells. The project also involves 11 production installations and laying of a pipeline. The EIA consultant has not been finalized as of now. Further RFQs are likely in upcoming months.
8Project Event: RFQs for hiring EPC contractor for the laying down of pipeline and production installations are expected by June instead of March 2018.
RFQs for the mechanical equipment is expected by June 2018.
8Expenditure Approval: Q3/2016
8RFQ Date: Jun/2018
8Release Date: Jul/2018
8Start Date: Q4/2018
8Completion Date: Sep/2021
Click here for more details

8 Project Name: Development Drilling Project
8Project Description: Promoter is planning the development of an oil field. The project involves workover of 3 temporarily abandoned wells and development drilling 6 wells spread over an area of 20 sq. km. Moreover, the project also involves laying of pipelines for connecting the oil field with the nearest production facility. After a long delay on account of a few resignations, the RFQs for the project are expected soon.
8Project Event: RFQ for hiring a consultant for EIA services is expected by May end instead of March end 2018.
RFQ for hiring rigs and other oilfield services is expected by June instead of March end 2018.
8Expenditure Approval: Q2/2017
8RFQ Date: May/2018
8Release Date: Jun/2018
8Start Date: Q3/2018
8Completion Date: Q4/2019
Click here for more details

8Project Name: Oil Field Development
8Project Cost: Rs 1700 crore
8Project Description: The Promoteris planning exploratory drilling of 150 wells spread over several blocks. The locations are proposed to be drilled by promoter owned electrical type rigs but it depends on the availability of rigs at the time of drilling activity. An EIA Consultant has already been hired for the project. Further RFQs are expected shortly.
8Project Event: RFQs for the hiring of Oil field services such as Drilling services, cementing services, material supplies etc are expected by Q3:2018.
8Expenditure Approval: Q3/2017
8RFQ Date: Q3/2018
8Release Date: Q3/2018
8Start Date: June/2019
8Completion Date: Dec/2021
Click here for more details


**********************************

Back  |  Top