Mar 15: 8Project Name: Gas Turbine Power Station - O&M Supply Project 8Project Cost: 5 crores 8Project Description: The owner's replacement of an existing inlet air filter house in the 101 MW Gas Turbine Power Station is on hold due to delay in getting administrative approval. The procurement team of the owner will come out with a bid for the new inlet air filter house soon. 8Project Event: RFQ for purchase of a new inlet air filter house is expected by May 2018, instead of March 2018. 8Expenditure Approval: Q4:2017 8RFQ Date: May/2018 8Release Date: Jul/2018 8Start Date: Sep/2018 8Completion Date: Oct/2018 Click here for more information 8Project Name: Hydro Power Station - Renovation, Modernization and Life Extension Project 8Project Cost: 50 crores 8Project Description: The owner is going on with renovation, modernization and life extension works for a 90 MW Hydo Power Station. The owner will come out with bids for short lead equipment for runner and brake-jack system. 8Project Event: RFQs for brake-jack system and short lead equipment of runner are expected by May 2018 8Expenditure Approval: Q1:2017 8RFQ Date: May/2018 8Release Date: Q3:2018 8Start Date: Q2:2017 8Completion Date: Q1:2020 Click here for more information Contact Update : Contacts are an important tool in the hands of a business development manager. We put in great efforts to get you validated telephone numbers of departmental heads within the power industry. 8A new finance general manager in a major NTPC plant. He is likely to be involved with business development activity in the plant. Click on details for more information