Mar 13: Ammonia-Urea Energy Saving Project  
8Cost - Rs 347 Crore
8Project Event: EOI has already been released for an LSTK contractor in November 2017, the techno-commercial discussion is going on with bidders and price bid has not beent opened yet, finalization is due in May 2018.
Click here for more information
Sulphuric Acid and Captive Power Unit Expansion Project  
8Cost - Rs 300 Crore
8Project Event: RFQ for EPC contractor is likely to be released in June 2018.
Click here for more information
Single Super Phosphate Greenfield Project   
8Cost - Rs 10 Crore
8Project EventRFQ for a contractor is likely to be released in April in place of March 2018
Click here for more information


**********************************