Mar 13: 8Project Name: Greenfield Hydroelectric Power Project 8Project Cost: 1000 crores 8Project Description: The owner's 191 MW ( 3x50.33 MW and 2x20 MW) greenfield hydroelectric power station is getting hampered on account of delay in land acquisition. Forest Clearance for diversion of forest land is also pending. DPR has been prepared and concurred by CEA. A German development financial institution has not sanctioned the loan to the company. EC is expected to be elicited in Q3 2018. The owner will come out with package wise bids soon. 8Project Event: RFQs for civil works are expected by Q2 2018, instead of March 2018. 8Expenditure Approval: 2014 8RFQ Date: Q2:2018 8Release Date: Q3:2018 8Start Date: Q3:2019 8Completion Date: Q4:2023 Click here for more information 8Project Name: Thermal Power Plant - Long Term Maintenance Contract 8Project Cost: 3 crores 8Project Description: The developer is going on with construction activities for a 2400 MW (3x800 MW) super-critical thermal power complex. Two of the units of 800 MW each are already been commissioned. The third unit of 800 MW is expected to get commissioned by September 2018. Bids for Long term contract for electrical and C&I have been out. The owner will come out with RFQs for long term maintenance contract of water treatment plant, chimney, fire protection system for a period of three years soon. 8Project Event: RFQs for Long term contract for water treatment plant, chimney, Fire protection system are expected by May 2018. 8Expenditure Approval: Q3:2016 8RFQ Date: May/2018 8Release Date: Jun/2018 8Start Date: Nov/2018 8Completion Date: Nov/2021 Click here for more information Contact Update : Contacts are an important tool in the hands of a business development manager. We put in great efforts to get you validated telephone numbers of departmental heads within the power industry. 8A group general manager of project of a major NTPC's plant has been promoted to the post of Executive Director. Click on details for more information