Mar 13: 8Project Name: Pipeline Expansion Project 8Project Cost: Rs 8086 Crore 8Project Description: An owner along with EPMC contractor is carrying out construction activities for the expansion of the Gas Pipeline. The pipeline has an initial capacity of 54.86 MMSCMD but is to be revamped up to 78.25 MMSCMD. The project involves the construction of a 2,042km gas pipeline that will be done in two phases phase- I include the construction of 1,650km of trunk line and phase- II 350km of spur lines. RFQ for the gas compressor, SCADA and Telecom services is already out. 8Project Event: RFQ for the contractor for the dispatch and receiving terminals and intermediate pigging stations is to be expected in June 2018. 8Expenditure Approval: Q2:2015 8RFQ Date: Jun/2018 8Release Date: Aug/2018 8Start Date: Q2:2017 8Completion Date: Q2:2019 Click here for more details. 8Project Name: Greenfield 2G Ethanol Bio-Refinery 8Project Cost: Rs 800 Crore 8Project Description: An owner along with PMC contractor and licensor is planning to construct an ethanol plant based on the DBT-ICT 2G Ethanol technology developed indigenously to produce 100 KL fuel-grade ethanol per day, primarily from biomass and will use approximately 400 MTPD of biomass per year. RFQ for the LSTK contractor is already out and selection process is going on. 8Project Event: RFQ for biomass is expected by June 2018. 8Expenditure Approval: Q2:2017 8RFQ Date: Jun/2018 8Release Date: Jul/2018 8Start Date: Q2:2018 8Completion Date: Q1:2021 Click here for more details. 8Project Name: Greenfield Ethylene Recovery Unit Project 8Project Cost: Rs 3800 Crore 8Project Description: An owner along with EPCM contractor and licensor is carrying out engineering activities to construct an Ethylene Recovery Unit with a capacity of 180 KTPA and Mono Ethylene Glycol Unit with a capacity of 332 KTPA at its refinery. RFQ for the equipment is already out. 8Project Event: RFQ for the piping and equipment erection work is expected in June 2018. 8Expenditure Approval: Q4:2016 8RFQ Date: Jun/2018 8Release Date: Jul/2018 8Start Date: Q3:2017 8Completion Date: Q3:2020 Click here for more details. 8Project Name: Greenfield LPG Bottling plant project 8Project Cost: Rs 161 Crore 8Project Description: An owner along with PMC contractor is planning to install an LPG Bottling Plant with a capacity of 120000 MTPA by installing 3 X 600 MT mounded storage vessels. RFQ for the equipment is already out. 8Project Event: RFQ for structural and civil work is expected by July 2018. 8Expenditure Approval: Q3:2017 8RFQ Date: Jul/2018 8Release Date: Aug/2018 8Start Date: Q1:2018 8Completion Date: Q1:2020 Click here for more details.