Software updates: Down stream opportunities ahead
Mar 12: 8Project Name: Refinery Greenfield Project
8Project Cost: Rs 43129 Crore
8Project Description: An owner is planning to install a 9 MMTPA grass-root refinery cum petrochemical complex. Engineers India Limited was appointed as consultant for preparing the DFR. Licensor selection will be done unit wise. RFQ for the Licensor selection is already out.
8Project Event: RFQ for the route survey of the crude oil pipeline is expected by April 2018.
RFQ for PMC contractor is expected by October 2018.
RFQ for the LSTK contractor is expected by Q1 2019.
8Expenditure Approval: Q4:2016
8RFQ Date: Apr/2018
8Release Date: May/2018
8Start Date: Q1:2019
8Completion Date: Q4:2023
Click here for more details.

8Project Name: Greenfield 2G Bio-Refinery
8Project Cost: Rs 600 Crore
8Project Description: An owner along with PMC contractor and licensor (not the one which has so far grabbed most of the projects) is planning to construct an ethanol plant based on the DBT-ICT 2G Ethanol technology developed indigenously to produce 100KL fuel-grade ethanol per day, primarily from biomass, and it will use approximately 450 tons of biomass per day. A slight delay is expected in the requirement of equipment due to delay in the selection of LSTK contractor for which tenders are already out. Now environmental clearance is expected by June 2018.
8Project Event: RFQ for long lead items is expected by May 2018 instead of March 2018.
8Expenditure Approval: Q1:2017
8RFQ Date: May/2018
8Release Date: Jul/2018
8Start Date: Q2:2018
8Completion Date: Q1:2021
Click here for more details.

8Project Name: Greenfield POL Terminal Project
8Project Cost: Rs 322 Crore
8Project Description: An owner is planning to augment the existing Terminal for storage & dispatch of petroleum products and Rail loading gantry with automation. The Construction of total storage capacity of 2,13,316 KL will be done in two phases that are Phase I - 1,60,416 KL & Phase II - 52,900 KL. Phase-I is to be commissioned shortly. A private company is hired for the automation.
8Project Event: RFQ for a PMC contractor is expected by August 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Q4:2018
8Completion Date: Q4:2020
Click here for more details.


**********************************