All content in this website is sourced legitimately

Page No: 1
Software updates: Oil and Gas Projects.
Mar 06: 8 Project Name: Oil Field Development.
8Project Cost: Rs 2800 Crore.
8Project Description: Promoter is planning the development of an oil field. The project involves development drilling of 70 wells, 10 production installations and laying of approximately 190 km of pipelines. Currently, the project is in pre-clearance phase. The Environmental Clearance for the project is expected by June 2018. The process of hiring an EPC contractor for production installation and the pipeline laying is expected to begin soon. RFQ for the rigs, Xmas Trees, Cementing, Wireline, Drill Collar etc is expected shortly.
8Project Event: RFQs for EPC contractor for production installation and the pipeline network are expected by June instead of March 2018.
RFQs for hiring services for rigs and equipment are expected by July instead of April 2018.
8Expenditure Approval: Q3/2017
8RFQ Date: Jun/2018
8Release Date: Jul/2018
8Start Date: May/2019
8Completion Date: Dec/2021
Click here for more details

8 Project Name: Captive Solar Power Unit
8Project Description: Promoter is planning the installation of a 5MW captive Solar Power Unit. Currently, the project is in initial stage. As of now feasibility report for the project has not been prepared. The project will involve installation of solar panels and other power generation units in the existing premises of the promoter. The project will have to be executed on turnkey basis. Moreover, a slight delay is expected in RFQ release on account of delay from Head Office as the feasibility study part of the project is still to be completed from their end. Further RFQs for the project are expected shortly.
8Project Event: RFQ for hiring the LSTK contractor for the project is expected by June 2018 instead of March 2018.
8Expenditure Approval: Nov/2017
8RFQ Date: Jun/2018
8Release Date: Jul/2018
8Start Date: Q4/2018
8Completion Date: Q2/2019
Click here for more details

8Project Name: Oil Field Development
8Project Cost: Rs 2150 crore.
8Project Description: The Promoter is planning to drill 70 Nos. of onshore oil & gas wells along with laying of associated pipelines. A part of the block covers a Wildlife Sanctuary. The application for Wildlife Clearance is under process. An EIA Consultant has already been hired for the project. Further RFQs are expected shortly.
8Project Event: RFQs for hiring an EPC Contractor is expected by Q3/2018.
8Expenditure Approval: Q4/2017
8RFQ Date: Q3/2018
8Release Date: Q3/2018
8Start Date: Oct/2019
8Completion Date: June/2022
Click here for more details
8Project Name: Refinery Greenfield Expansion Project
8Project Cost: Rs 8300 Crore
8Project Description: An owner is planning to expand its refinery from 6 MMTPA capacity to 9 MMTPA capacity. A private company was appointed to prepare the Pre-feasibility Report. Further RFQ will be expected soon. Currently, surveying work is going on.
8Project Event: RFQ for Licensor selection is to be expected by April 2018.
8Expenditure Approval: Q1:2017
8RFQ Date: Apr/2018
8Release Date: May/2018
8Start Date: Q3:2018
8Completion Date: Q3:2023
Click here for more details.

8Project Name: Brownfield LPG Bottling Plant
8Project Cost: Rs 143 Crore
8Project Description: An owner along with EPC contractor Engineers India Limited is planning to expand its existing LPG capacity from 11 TMTPA to 60 TMTPA in its LPG bottling plant. RFQ for all the equipment is already out.
8Project Event: RFQ for mechanical work is expected by June 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: Jun/2018
8Release Date: Jul/2018
8Start Date: Q1:2018
8Completion Date: Q1:2020
Click here for more details.


**********************************