Mar 01: 8Project Name: Greenfield Hydroelectric Project
8Project Cost: 1000 crores
8Project Description: The owner is in talks with Asian Development Bank for a 120 MW (2*55 MW surface power-house + 2*2.5 MW+1*5 MW auxiliary power-house) hydroelectric greenfield hydro power plant for release funds for the project. Forest Clearance is pending. Bids for civil and infrastructure works are expected soon.
8Project Event: RFQ for civil and infrastructure package is expected by mid March 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: 20/Mar/2018
8Release Date: Q3:2018
8Start Date: Q2:2019
8Completion Date: Q4:2023
Click here for more information
8Project Name: Hydroelectric Power Greenfield Project
8Project Cost: 4000 crores
8Project Description: The promoter is setting up a 540 MW (4*135 MW) Hydroelectric Power Station. Bids for electro-mechanical package have already been floated in November 2017 but due to less participation of bidders and more time being consumed in pre-bid meetings, the bidding date will be extended for the E&M package for more bidders to participate. Work at the site is slated for Q3 2018.
8Project Event: The bidding date will be extended to June 2018 of an electro-mechanical package for more bidders to participate.
8Expenditure Approval: Sep/2014
8RFQ Date: 15/Nov/2017
8Release Date: Jul/2018
8Start Date: Q3:2018
8Completion Date: Q1:2024
Click here for more information
Business Opportunities in Renewable Sector : RfS to come up by Q3 2018
8A renewable sector state promoter is planning to establish a grid-connected solar park of capacity 500 MW .
8Lands have been identified.
8DPR works are underway.
8Request for Selection (RfS) bids to take place.
8The owner shall come out with technical bid and NIT for PPA after RfS bids.
The same promoter is also looking a hybrid solar-cum-wind project in the state with a capacity of between 500-1000 MW.
8Land surveys are currently on, after which the exact quantum of power to be bided out will be determined
Click on Reports for more


**********************************