Software updates: Oil and Gas Projects
Feb 27: 8Project Name: Refinery Greenfield Ethylene Recovery Unit Project
8Project Cost: Rs 3800 Crore
8Project Description: An existing company along with EPCM contractor and licensor is carrying out engineering activities to construct an Ethylene Recovery Unit with a capacity of 180 KTPA and Mono Ethylene Glyco Unit with a capacity of 332 KTPA at its refinery. RFQ for the equipment is already out.
8Project Event: RFQ for structural steelwork is expected by March 2018.
8Project Event: RFQ for the piping and equipment erection work is expected June 2018.
8Expenditure Approval: Q4:2016
8RFQ Date: Mar/2018
8Release Date: Apr/2018
8Start Date: Q3:2017
8Completion Date: Q3:2020
Click here for more details.
8Project Name: Greenfield LPG Bottling Plant Project
8Project Cost: Rs 120 Crore
8Project Description: An existing company along with EPC contractor is planning to set an LPG bottling plant with a capacity of 1500 MTPA by installing 3 X 500 MT mounded storage vessels. RFQ for the equipment is already out.
8Project Event: RFQ for erection and installation work is to be expected by May 2018.
8Expenditure Approval: May/2017
8RFQ Date: May/2018
8Release Date: Jun/2018
8Start Date: Q1:2018
8Completion Date: Q3:2019
Click here for more details.

8Project Name: LPG Bottling Plant Expansion Project
8Project Cost: Rs 32 Crore
8Project Description: An existing company is planning to expand its existing LPG bottling plant from 1000 MTPA to 2800 MTPA. Environmental Clearance is expected by April 2018. At present selection of EPC contractor is going on after that requirement of equipment will be out.
8Project Event: RFQ for equipment is expected by May 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: May/2018
8Release Date: Jun/2018
8Start Date: Q2:2018
8Completion Date: Q2:2019
Click here for more details.


**********************************