Rs 700 crore greenfield POL terminal: FEED RFQ in May
Feb 26: 8Project Name: Greenfield POL Terminal Project 8Project Cost: Rs 672 Crore 8Project Description: An owner along with EPMC contractor is planning to install a greenfield POL storage terminal with a capacity of 190000 KL. 8Project Event: RFQ for the front-end engineering design development (FEED) is expected by May 2018. 8Expenditure Approval : Q1:2017 8RFQ Date : May/2018 8Release Date: Jun/2018 8Start Date : Q2:2018 8Completion Date : Q2:2021 Click here for more details