Software Updates: Get key contacts and data on downstream projects coming up ahead
Feb 23: 8Project Name: Pipeline Expansion Project
8Project Cost: Rs 2485 Crore
8Project Description: An existing company  is planning to expand its pipeline to the proposed POL Terminal while also expanding the throughput capacity from 5.682 MMTPA to 8 MMTPA. Earlier the TOR was returned because of use of hazardous materials in the application but after revision, the TOR was issued. A private company has been hired as an EPMC contractor for that Basic Design, Detailed Engineering, Procurement, Construction Supervision, Commissioning Assistance and Project Management Services. At present Basic design, development is going on.
8Project Event: RFQ for the mainline pipes is expected by September 2018.
8Expenditure Approval : Q1:2017
8RFQ Date : Sep/2018
8Release Date: Oct/2018
8Start Date : Q2:2018
8Completion Date : Q2:2021
Click here for more details.
8Project Name: Greenfield 2G Ethanol Bio-Refinery
8Project Cost: Rs 121 Crore
8Project Description: An existing company has hired a PMC contractor to work with already selected licensor to construct an ethanol plant based on the DBT-ICT 2G Ethanol technology developed indigenously to produce 100 KL fuel-grade ethanol per day, primarily from biomass and will use approximately 72 MTPD of biomass per year. At present, selection of LSTK contractor is going on.
8Project Event: RFQ for the biomass supply is expected by mid of March 2018.
8Expenditure Approval: Q2:2017
8RFQ Date : Mar/2018
8Release Date: Apr/2018
8Start Date : Q2:2018
8Completion Date : Q2:2020