Feb 21: 8Project Name: Greenfield Super Thermal Power Station
8Project Cost: Rs 10000 crore.
8Project Description: A 1400 MW greenfield super-critical thermal power plant is on hold due to delay in preparation of NIT. The owner will come out with package wise bids for BTG, BoP, civil and FGD. The owner will come out with civil works bid package soon. Start-up is slated for Q2 2019.
8Project Event: RFQs for civil work and transportation services are expected in Q2 2018, instead of Q1 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Q2:2018
8Release Date: Q3:2018
8Start Date: Q2:2019
8Completion Date: Q2:2023
Click here for more details
8Project Name: Power House Maintenance Project
8Project Cost: Rs 15 crore.
8Project Description: Promoter has planned a 21-day scheduled maintenance of a unit in a 1300 MW river bed head power house, which includes overhauling of auxiliary parts of the turbine-generator set, tunnel lining, among others.
8Project Event: RFQs for equipment required are expected by second week of March 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: 10/Mar/2018
8Release Date: 25/Mar/2018
8Start Date: 4/Apr/2018
8Completion Date: 24/Apr/2018
Click here for more details


**********************************

Back  |  Top