Feb 19: Co-generation Greenfield Project 8Cost: Rs 20 crore 8Preject Description: A Fertilizer company has elicited an environmental clearance in December 2018 for its greenfield co-generation unit with a capacity 3.5 MW in India.The project is waiting for capital approval, and it is likely to be the granted in April 2018. 8Project Event: RFQ for a contractor is likely to be released in May 2018 Click here for more information Single/Triple Super Phosphate Greenfield Project 8Cost - Rs 30 Crore 8Project Event: Detail Project Report preparation is going on and proposal for an environmental clearance is likely to be submitted in March 2018. Tender for an EPC contractor is likely to be released in March 2018. Click here for more information Phosphoric Acid Greenfield Project 8Cost - Rs 10 Crore 8Project Event: RFQs for an EPC contractor is likely to be released in March 2018. Click here for more information