Software updates: Fertilizer projects
Feb 14: Ammonia-Urea Energy Saving Project
8Cost - Rs 481 Crore
8Project Event: The proposal for environmental clearance has been accepted in February 2018 and the selection process for the LSTK contractor is on and techno-commercial discussion is completed and price bid was opened in January 2018, Finalization is due in March 2018.
Click here for more information
Ammonia-Urea Energy Saving Project      
8Cost - Rs 250 Crore
8Project Event: RFQs for the EPC contractor is likely to be released in April 2018 in place of January 2017 due to lack of funds. The company is still struggling for capital approvals and is hoping that the government will provide at least 2 to 3 year to achieve the energy norms target

**********************************