Feb 09: 8Project Name: Hydro Power Station Maintenance Project (Unit-3) 8Project Cost: 15 crores 8Project Description: The owner has planned a 20-day scheduled maintenance of Unit-3 (200 MW) in the 1200 MW (6*200 MW) river bed power house which includes overhauling of auxiliary parts of the turbine-generator set, bearing sets, tunnel lining, among others. 8Project Event: RFQs for equipment required are expected by mid-February 2018. 8Expenditure Approval: Q2:2017 8RFQ Date: 15/Feb/2018 8Release Date: 25/Feb/2018 8Start Date: 9/Mar/2018 8Completion Date: 29/Mar/2018 Click here for more information 8Project Name: Greenfield Multipurpose Project 8Project Cost: 1000 crores 8Project Description: The owner's 300 MW (3*100 MW) greenfield multipurpose project is on hold due to delay in site survey works at the site. PFR has been submitted to CWC which is under appraisal. The project developer will come out with a requirement for a consultant for DPR preparation soon. 8Project Event: RFQ of a consultant for preparation of DPR is expected by Q3 2018, instead of Q1 2018. 8Expenditure Approval: Q4:2017 8RFQ Date: Q3:2018 8Release Date: Q4:2018 8Start Date: Q2:2020 8Completion Date: Q3:2025 Click here for more information