Software Update : Power Projects
Feb 08: 8Project Name: Gas Power Station Maintenance Project
8Project Cost: 12 crores
8Project Description: The owner has planned a 10-days scheduled maintenance of Unit-3 in the 127.20 MW Gas Based Power Station covering minor inspection (type A) of equipment which includes overhauling of auxiliary parts of the gas turbine set and air filter cleaning of compressor parts.
8Project Event: RFQ for short lead equipment required are expected by mid-February 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: 12/Feb/2018
8Release Date: 25/Feb/2018
8Start Date: 1/Mar/2018
8Completion Date: 10/Mar/2018
Click here for more information
8Project Name: Hydroelectric Greenfield Project : PPA delays RFQ
8Project Cost: 200 crores
8Project Description: The owner's 52 MW (2x26 MW) greenfield hydroelectric plant has been held up on account of a delay in signing of the power purchase agreement. Environment Clearance is likely to be elicited by Q3 2018. Project kick off date is expected in early 2020. The developer will come out with a package wise bids after getting EC appraisal.
8Project Event: RFQs for civil works are expected to be out by Q1 2019, instead of Q1 2018.
8Expenditure Approval: Q4:2017
8RFQ Date: Q1:2019
8Release Date: Q3:2019
8Start Date: Q2:2020
8Completion Date: Q3:2024