Project Name:
Drilling Site Development.
8Project Cost: Rs 200 Crore.
8Project Description: A private promoter is planning the development of an oil field in Assam. The project is expected to start by June 2019. 
8Project Event: RFQs for hiring an EIA Consultant for the project is expected by August 2018.
RFQ for hiring Rigs and other oilfield services is expected by December 2018.
8Expenditure Approval: Q2/2018
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Jun/2019
8Completion Date: Jun/2021.
Click here for more details

8Project Description: Promoter is looking at an onland field, involving development drilling of oil wells, construction of surface facilities in the already existing CTF and the laying of a 6-inch pipeline from the oil field to the CTF.
8Project Event: RFQs for hiring an EPC contractor for laying the pipeline are expected by February end 2018 instead of January 2018 as projected earlier.
Click here for more details
8 Project Name: Refinery BS VI Up-gradation Project
8Project Cost: Rs 3200 Crore.
8Project Description: An existing company along with EPCM contractor and licensor is carrying out detailed engineering work. RFQ for the equipment is already out.
8Project Event: RFQ for electrical and instrumentation work is expected by April 2018.
8Expenditure Approval: Q3/2016
8RFQ Date: Apr/2018
8Release Date: May/2018
8Start Date: Q1:2018
8Completion Date: Q3:2020
Click here for more details
8 Project Name: Refinery Modernization Project
8Project Cost: Rs 21000 Crore.
8Project Description: An existing company along with PMC contractor and licensor is carrying out engineering activities. A private company has been appointed as EPCC contractor for Crude Distillation and Vacuum Distillation Unit.
8Project Event: RFQ for the LSTK contractor for VGO Unit and Hydrogen Unit is expected by April 2018.
8Expenditure Approval: Q4/2016
8RFQ Date: Apr/2018
8Release Date: May/2018
8Start Date: Q2:2017
8Completion Date: Q2:2020