Software updates: Oil and Gas Projects.
Feb 05: 8Project Name: Offshore Field Development
8Project Cost: Rs 500 crore.
8Project Description: Promoter is planning the development of an Offshore field. The block had been awarded to the company under the Discovered Small Fields round 2016. The Field Development Plan (FDP) for the block is yet to be submitted. Currently, promoter is in the process of carrying out an analysis so as to evaluate possible oil reserves.  Drilling for the project will be carried out using a jack-up rig. The project is expected to start by August 2019. Further RFQs are expected shortly.
8Project Event: RFQs for hiring an EIA Consultant for the project is expected by September 2018.
RFQs for hiring an EPCM contractor is expected by October 2018.
8Expenditure Approval: Q2/2018.
8RFQ Date: Sept/2018.
8Release Date: Oct/2018.
8Start Date: Aug/2019.
8Completion Date: Aug/2022.
Click here for more details

8Project Name: Oil Field Development.
8Project Cost: Rs 200 crore
8Project Description: Promoter is planning the development of an oil field. The block  had been awarded to the company under the Discovered Small Fields round 2016. Currently, promoter is in the process of carrying out an analysis so as to evaluate possible oil reserves. The project is expected to start by July 2019. Further RFQs are expected shortly.
8Project Event: RFQs for hiring an EIA Consultant for the project is expected by September 2018.
RFQs for hiring Rigs and other oilfield services is expected by December 2018.
8Expenditure Approval: Q2/2018
8RFQ Date: Sep/2018
8Release Date: Oct/2018
8Start Date: Jul/2019
8Completion Date: Jul/2021
Click here for more information

8Project Name: Oil Field Drilling.   
8Project Cost: Rs 700 crore
8Project Description: Promoter is planning exploratory drilling of 18 wells in an onland block. The project involves exploratory drilling of 18 onshore wells and has been listed out as an extension project for the already existing 12 well drilling project. Currently, the project is in clearance phase. The environment clearance for the project is expected by Q1 2018. The forest clearance and CRZ clearance for the project is not required. RFQ for the following equipment are expected shortly for Cementing Unit, Blow Out Preventer, Pressure Gauge, Valves and Well Chemicals. There has been a slight change in the RFQ dates as well. Further RFQs are expected shortly.
8Project Event: RFQ for the equipment is expected by March 2018 instead of January 2018
8Expenditure Approval: Q3/2016
8RFQ Date: Mar/2018
8Release Date: Apr/2018
8Start Date: Jun/2018
8Completion Date: Q4/2022
Click here for more information
8Project Name: Refinery BS VI Motor Spirit Block Upgradation
8Project Cost: Rs 3313 crore.
8Project Description: An existing company along with EPCM contractor is carrying out engineering activities to upgrade its BS V Motor spirit block to BS VI Motor Spirit block at its refinery, involving the construction of a Naphtha hydrotreater unit, Continuous catalytic reformer (CCR) unit, and a Light naphtha isomerization unit. RFQ for the procurement of equipment is already out.
8Project Event: RFQ for erection and installation work is expected by March 2018.
8Expenditure Approval: Q2:2016.
8RFQ Date: Mar/2018.
8Release Date: Apr/2018.
8Start Date: Q4:2016.
8Completion Date: Q2:2020.
Click here for more details
8Project Name: Refinery Debottlenecking Greenfield
8Project Cost: Rs 2519 crore.
8Project Description: An existing company along with EPC contractor is currently conducting engineering activities for a low cost debottlenecking of its refinery, raising its capacity from 6 MMTPA to 7.8 MMTPA. RFQ for the equipment is already out.
8Project Event: RFQ for erection and installation work is expected by April 2018.
8Project Event: RFQ for electrical and instrumentation work is expected by June 2018.
8Expenditure Approval: Q4:2016.
8RFQ Date: Apr/2018.
8Release Date: May/2018.
8Start Date: Q2:2017
8Completion Date: Q4:2018.
Click here for more details