Jan 30: 8Project Name: Refinery Bulk Grid Power Project
8Project Description: An existing company is planning on importing bulk grid power at 220 KV at its refinery. Currently, bids for consultancy of infrastructure work has already been floated. Survey and investigation works are going on the ground for implementation of 220 KV switchyard. The process will be done in two phases OSBL (Outside Battery Limit) and another is ISBL (Inside battery limit) The OSBL job shall be executed by a State Power Transmission Company while the ISBL job will be completed by the refinery owner. The ISBL job will be done in LSTK mode.
8Project Event: RFQ for the designing, construction and material supply for switchyard equipment is expected by Q3 2018.
8Expenditure Approval: Q1:2017
8RFQ Date: Q3:2018
8Release Date: Q4:2018
8Start Date: 2019
8Completion Date: 2021
Click here for more details.
8Project Name: Greenfield 2G Ethanol Bio-Refinery
8Project Cost: Rs 800 Crore
8Project Description: An existing company along with the PMC contractor and licensor is planning to construct an ethanol plant based on the DBT-ICT 2G Ethanol technology developed indigenously to produce 100 KL fuel-grade ethanol per day, primarily from biomass and will use approximately 400 MTPD of biomass per year.
8Project Event: RFQ for LSTK contractor is expected by March 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: Mar/2018
8Release Date: Apr/2018
8Start Date: Q2:2018
8Completion Date: Q2:2021
Click here for more details.

8Project: RFQ for erection and installation work for POL Terminal is expected by April 2018. The requirement of equipment is already out.
Click here for more details
8Project Name: Oil and Gas Field Site Development
8Project Cost: Rs 2000 crore.
8Project Description: Promoter is planning the development of an Oil and Gas field. The project involves development drilling of 54 onshore wells, 02 production installations and laying of 250 km infield pipeline. Currently, the project is in pre-clearance phase.The Environmental Clearance for the project is expected by October 2018. The process of hiring an EPC contractor for production installations and the pipeline laying is expected to begin soon. RFQ for the Drilling Rigs, Blowout Controller, Xmas Trees, Cementing, Wireline, Drill Collar etc is expected shortly.
8Project Event: RFQs for hiring an EIA consultant is expected by Feb 2018.
RFQs for hiring Rigs and other equipment is expected by July 2018.
8Expenditure Approval: Q3/2017
8RFQ Date: Feb/2018
8Release Date: Mar/2018
8Start Date: Mar/2019
8Completion Date: Apr/2021
Click here for more details

8Project Name: Offshore Development Project: RFQs changed to February.
8Project Cost: Rs 4000 crore
8Project Description: RFQs for a deepwater chemical management system for an offshore development drilling project has been delayed a bit. Further RFQs are expected shortly.
8Project Event: RFP for hiring an LSTK contractor for the deep water chemical management system is expected by February end 2018 instead of January 2018..
8Expenditure Approval: Q2/2013
8RFQ Date: Feb/2018
8Release Date: Mar/2018
8Start Date: Q2/2018
8Completion Date: Q4/2018
Click here for more information

8Project Name: Development Drilling Project.
8Project Cost: Rs 800 crore
8Project Description: RFQs for the promoter's oil fields development plan have been delayed a bit. The TOR for the project has already been granted. The process of hiring an EPC contractor for production installation and the pipeline laying is expected to begin soon. RFQ for the Rigs, Blow-Out Controller, Xmas Trees, Cementing, Wireline, Drill Collar etc is expected shortly.
8Project Event: RFQ for EPC contractor for production installation and installation of a pipeline network is expected by March 2018.
RFQ for hiring services for rigs and equipment is expected by April 2018.
8Expenditure Approval: Q2/2017
8RFQ Date: Mar/2018
8Release Date: Apr/2018
8Start Date: Q4/2018
8Completion Date: Q4/2020