Software updates: Oil and Gas Projects.
Jan 29: 8Project Name: Refinery INDMAX Project
8Project Cost: Rs 4185 Crore
8Project Description: An existing company along with EPC contractor and licensor  is carrying out engineering activities to construct the following new units: INDMAX unit of 740 TMTPA, Prime G+(IGHDS) of 312 TMTPA, NHT unit of 235 TMTPA, SRU of 80 TMTPA, SDS of 59 TMTPA and revamping of the DHDT from 1200 TMTPA to 1800 TMTPA, CRU from 160 TMTPA to 200 TMTPA as well as crude processing capacity enhancement from 2.35 MMTPA to 2.7 MMTPA in its refinery. RFQ for equipment is already out. At present civil work is going on.
8Project Event: RFQ for erection and installation work is expected by April 2018.
8Expenditure Approval: Q3:2016
8RFQ Date: Apr/2018
8Release Date: May/2018
8Start Date: Q1:2018
8Completion Date: Q2:2020
Click here for more details.
8Project Name: Refinery BS VI Motor Spirit Block Upgradation
8Project Cost: Rs 3313 Crore
8Project Description: An existing company along with EPCM contractor is carrying out engineering activities to upgrade its BS V Motor spirit block to BS VI Motor Spirit block at its refinery, involving the construction of a Naphtha hydrotreater unit, Continuous catalytic reformer (CCR) unit, and a Light naphtha isomerization unit. RFQ for the procurement is already out. RFQ for the Reciprocating Compressor for a special tailor-made purpose is coming soon.
8Project Event: RFQ for Reciprocating compressor is expected by February 2018.
8Project Event: RFQ for erection and installation work is expected by March 2018.
8Expenditure Approval: Q2:2016
8RFQ Date: Feb/2018
8Release Date: Mar/2018
8Start Date: Q4:2016
8Completion Date: Q2:2020
Click here for more details.
8 Project Name: Oil Field Development
8Project Cost: Rs 100 Crore.
8Project Description: Promoter is planning the development of an oil field. The block was awarded to the company under the Discovered Small Fields round (DSF) in 2016. The project involves development drilling of oil wells and laying of an infield pipeline to connect with the nearest production facility (GGS). Currently, the project is in pre-clearance phase. The owner is in process of carrying out an analysis of oil fields so as to estimate the reservoir potential. Production from the block is expected to start by the end of 2021. Further RFQs are expected shortly.
8Project Event: RFQs for the hiring of EIA Consultant is expected by August 2018.
RFQs for the hiring of Rigs and other oilfield services are expected by January 2019.
8Expenditure Approval: Q2/2018
8RFQ Date: Aug/2018
8Release Date: Sep/2018
8Start Date: Jul/2019
8Completion Date: Aug/2021
Click here for more details

8 Project Name: Onshore Field Development.
8Project Description: RFQs for promoter's development field have been delayed a bit as the manpower hiring process is going on in the project for various roles on account of a few resignations. The block had been awarded to the company in small fields bid round 2016. A detailed study of the oil field to estimate possible reserves and production is expected shortly. The company is planning the study of the field prior to starting the production. An EOI is also expected for various drilling services. Further RFQs are expected shortly.
8Project Event: RFQ for hiring a consultant for oil field studies and analysis is rescheduled to February end 2018 from January 2018.
RFQ for EOI for various oil and gas services is expected by Q1 2018.
8Expenditure Approval: Q3/2017
8RFQ Date: Feb/2018
8Release Date: Mar/2018
8Start Date: Apr/2018
8Completion Date: Apr/2019
Click here for more details

8 Project Name: Drilling Site Hydrofracturing
8Project Description: RFPs for promoter's hydraulic fracturing work primarily in the oil fields have been delayed a bit. The requirement from promoter's end for Hydrofracturing services will be for lightweight ceramic/sintered bauxite proppant having a preferable mesh size of 20/40 & 16/30 respectively. The reservoir characteristics of the fields of the Asset have wide variations ranging from shallow depth to depth more than 2000m and more. An annual requirement of 1000 MT of proppant is expected from promoter's end.
8Project Event: RFP for the 20/40 proppant is expected by February end 2018 instead of January 2018.
RFP for the16/30 proppant is expected by March end 2018 instead of February 2018.
8Expenditure Approval: Sep/2017
8RFQ Date: Feb/2018
8Release Date: Mar/2018
8Start Date: Q2/2018
8Completion Date: Q2/2019
Click here for more details


**********************************