Jan 19: 8Project Name: Procurement of LP Turbine Blades in Thermal Power Station 8Project Cost: 15 crores 8Project Description: The owner is planning to procure new LP turbine blades in a 600 MW Thermal Power Station. The owner will procure a new LP turbine including fasteners in case of failure of existing turbine blades, as failure of LP turbine blades will result in shutdown of the unit. Administrative approval is awaited, after which the procurement team of the owner will come out with a bid for the LP turbine blades. 8Project Event: RFQ for purchase of a LP turbine blades is expected by March 2018. 8Expenditure Approval: Q3:2017 8RFQ Date: Mar/2018 8Release Date: Apr/2018 8Start Date: Jun/2018 8Completion Date: Jul/2018 Click here for more information 8Project Name: Greenfield Thermal Power Station 8Project Cost: 30000 crores 8Project Description: The owner along with EPC contractor is planning to construct a 4000 MW (5*800 MW) super-critical coal based greenfield Super Thermal Power Plant. Currently, material supply at the site has been started. TheEPC contractorhas already come out with bids for land development works. Boiler and Turbine will be given by the EPC contractor. Construction work at the ground is to start in next 4-5 months. The EPC contractor will come out with a BoP package, electrical equipment, and FGD package soon. 8Project Event: RFQs for a BoP package are expected by Q2 2018. 8Expenditure Approval: Q2:2014 8RFQ Date: Q2:2018 8Release Date: Q4:2018 8Start Date: Q3:2018 8Completion Date: Q2:2024 Click here for more information