Jan 17: 8 Project Name: Drilling Site Development 8Project Cost: Rs 260 Crore. 8Project Description: Promoter is planning the development of an oil field. The block was awarded to the company under the Discovered Small Fields (DSF) round in 2016. The project involves development drilling of oil wells and laying of an infield pipeline to connect with the nearest production facility (GGS). Currently, the project is in pre-clearance phase. Production from the block is expected to start by the end of 2020. Promoter does not have any prior experience in oil field development. Further RFQs are expected shortly. 8Project Event: RFQs for hiring a consultant for EIA services is expected by March 2018. RFQs for hiring workover rigs and drilling rigs is expected by March 2018. RFQs for hiring other oilfield services is expected by April 2018. 8Expenditure Approval: Q2/2018 8RFQ Date: Apr/2018 8Release Date: Jun/2018 8Start Date: Apr/2019 8Completion Date: Dec/2021 Click here for more details 8 Project Name: CBM Block Development 8Project Description: Promoter along with its partner is planning the development of a CBM Block by drilling a total of CBM wells. Promoter has already selected a strategic partner to undertake the development of the block. An overall quantity of 0.4 MMSCMD of gas has been envisaged to be produced from the project. Stragetic Partner company, in turn, had selected a US firm to carry out the feasibility study for the project. The consultant for EIA services is about to be finalized from the company's end. The drilling rig tender is also in finalization stage. Further RFQ's for the project are expected shortly. 8Project Event: RFQs for manpower requirement are expected by February end 2018. RFQs from promoter's end for various mechanical and electrical equipment are expected by March 2018. 8Expenditure Approval: Q1/2016 8RFQ Date: Feb/2018 8Release Date: Mar/2018 8Start Date: Q3/2018 8Completion Date: Q3/2021 Click here for more details 8Project Name: Refinery BS-VI Up-gradation Project 8Project Cost: Rs 1713 Crore 8Project Description: An existing company along with EPCM contractor and licensor is planning to construct the following new units: CCR of 400 TMTPA, Isomerisation unit of 200 TMTPA and revamping of HGU-I from 34 TMTPA to 53 TMTPA, Prime-G of 525 TMTPA, DHDS of 1100 TMTPA without any reduction its capacity to meet BS-VI Fuel Quality Up-gradation within the existing refinery. RFQ for the equipment is already out. 8Project Event: RFQ for civil work is expected by March 2018. 8Expenditure Approval: Q2:2016 8RFQ Date: Mar/2018 8Release Date: Apr/2018 8Start Date: Q2:2018 8Completion Date: Q2:2020 Click here for more details. 8Project Name: Greenfield LPG Bottling Plant Project 8Project Cost: Rs 137 Crore 8Project Description: An existing company is planning to install an LPG Bottling Plant with a capacity of 120000 MTPA by installing 3 X 350 MT mounded storage vessels. A slight delay in hiring the PMC contractor due to the land accusation process. 8Project Event: RFQ for Project Management Consultant is expected by May 2018. 8Expenditure Approval: Feb/2017 8RFQ Date: May/2018 8Release Date: Jun/2018 8Start Date: Q3:2018 8Completion Date: Q3:2020 Click here for more details.