Jan 16: 8Project Name: Thermal Power Station Maintenance Project (Unit-5) 8Project Cost: 15 crores 8Project Description: The owner has planned am 18-day scheduled mini overhaul of the Unit-5 (500 MW) in the 2630 MW Thermal Power Plant covering a mini overhaul of the complete complex in which equipment includes turbine bearings, refilling of gas for HP, IP, LP turbine cylinders, boiler linings, inspection of rotor blades, among others. 8Project Event: RFQ for short lead equipment is expected by February 2018. 8Expenditure Approval: Q2:2017 8RFQ Date: Feb/2018 8Release Date: Feb/2018 8Start Date: 14/Mar/2018 8Completion Date: 31/Mar/2018 Click here for more information 8Project Name: Gas Turbine Power Station - O&M Supply Project 8Project Cost: 7 crores 8Project Description: The owner is planning to replace an existing inlet air filter house in the 107.88 MW Gas Turbine Power Station. The existing inlet air filter house is in corroded condition and many holes have developed due to corrosion. At present these holes are covered by providing metal patches. Administrative approval is awaited, after which the procurement team of the owner will come out with a bid for the new inlet air filter house. The main equipment required will be Inlet air filtration system, evaporative cooler, transition piece. 8Project Event: RFQ for purchase of a new inlet air filter house is expected by March 2018. 8Expenditure Approval: Q4:2017 8RFQ Date: Mar/2018 8Release Date: May/2018 8Start Date: Sep/2018 8Completion Date: Oct/2018 Click here for more information