Jan 15: Phosphoric Acid Expansion Project: On hold 8Cost - Rs 1100 Crore 8Project Description:A Fertilizer Company is awaiting environmental clearance for its phosphoric acid expansion, from 50417 to 131744 MTPA. A preliminary pre-qualification process will be ongoing, subsequent to which a tender for an LSTK contract will be taken out. the equipment requirements for the phosphoric acid plant are Storage Systems, Soda Ash Silos, Rotary Dryers, Grinding Unit, Ball Mill, Mixing Tanks, Blending Unit, Wet Scrubber Unit, Venturi Scrubber Unit, Cyclone System, Air Pollution Control System, Vibro Shifter, Screens and Sieves, Conveyors and more. 8Project Event: The Project is on hold, likely to be active in Q3 2018. Click here for more information SSP Fertilizer Greenfield Project: RFQ likely today 8Cost - Rs 90 Crore 8Project Description: A Fertilizer Company is planning to re-release the tender for an EPC contractor for a greenfield Single Super Phosphate Fertilizer project with a capacity 800 MTPD at Pandoli in Rajasthan. The tender was floated earlier but at that time bidders did not fulfill the BEC requirements. The equipment requirements are Cranes, Hoppers, Feeders, Conveyors, Valves, Grinding Mills, Tanks, Separators, Pumps, ID Fans, Collectors, Generators, Mixers, Dens, Scrubbers, Screens, Elevators, Furnaces, Cyclones, Blowers, Belts, Weighing machines and more 8Project Event: RFQ for an LSTK contractor is likely to be released today. Click here for more information