Jan 11:
Ammonia-Urea
& Captive Power Plant Greenfield Project 8Cost -
Rs 10741 Crore 8Project
Description:A
Fertilizer Company is planning a greenfield coal-based ammonia-urea plant with a
capacity 2200 MTPD of ammonia, 3850 MTPD of urea and 70 MW of Captive power
plant. The consultant and process licensors have been appointed. The tender is
out for the LSTK contractor. 8Project
Event: RFQ for LSTK contractor was floated in May 2017 and the bid
closing date for Coal Gasification Plant for Generating Ammonia Syn. Gas &
Carbon Dioxide Gas is extended from 26 November 2017 to 28 February 2018 and the
ammonia-urea plant is extended from 9 January to 8 March 2018.
Click here for more information Ammonia-Urea Energy Saving Project 8Cost -
Rs 481 Crore 8Project
Description: Thermax, BHEL, Sterling & Wilson are in the race for an
energy saving project of Rashtriya Chemical and Fertilizer Ltd at its Trombay
Fertilizer Complex in Mumbai. Rashtriya Chemical and Fertilizer Ltd is planning
to reduce the energy consumption of its Ammonia and Urea units from 8.73 Gcal/MT
to 8.40 Gcal/MT and 6.75 Gcal/MT to 6.45 Gcal/MT respectively in India. The
capacity of the ammonia plant is 1045 MTPD and the urea capacity is 1000 MTPD.
The equipment requirements are 2 nos of GTG with a capacity 25 MW (ISO Rating),
2 nos of HRSG with a capacity 65 TPH, Replacement of turbine for the Benfield
Solution Pump in Ammonia with a new motor, De-aerator (2 nos.) with HP BFW Pump
motor set 2 x (1+1), One PRDS system for 12 ata to 4.5 ata in the Ammonia plant,
Modification in Power Distribution System. Environment clearance is awaited and
it will take about three months. 8Project
Event: The selection process for the LSTK contractor is on and
techno-commercial discussion is completed and price bid is likely to be opened
by the end of January 2018