Software updates: Oil and Gas Projects.
Jan 11: 8Project Name: Refinery Shutdown Project
8Project Cost: Rs 20 Crore
8Project Description: An existing company is planning for a 30-day shutdown of CDU-2 and FCC units from July 2018 at its refinery. This is a maintenance shutdown.
8Project Event: RFQ for a contractor is expected by April 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Apr/2018
8Release Date: May/2018
8Start Date: Jul/2018
8Completion Date: Aug/2018
Click here for more details.
8Project Name: Refinery BS-VI Upgradation Project
8Project Cost: Rs 497 Crore
8Project Description: An existing company along with EPC contractor and licensor has brought out an RFQ for equipment for a new FCC gasoline desulphurization unit with a capacity of 0.6 MMTPA and expansion of the DHDT unit from 1.8 MMTPA to 2.4 MMTPA at its refinery. Engineering activities are currently on in the project. Further RFQs are now awaited.
8Project Event: RFQ for erection and installation work is expected by March 2018.
8Expenditure Approval: Q4:2016
8RFQ Date: Mar/2018
8Release Date: Apr/2018
8Start Date: Q2:2017
8Completion Date: Jun/2019
Click here for more details.

8Project Name: Refinery Expansion Project
8Project Cost: Rs 27000 Crore
8Project Description: An existing company is planning to expand its existing 1 MMTPA refinery to 10 MMTPA by installing a new 9 MMTPA crude distillation unit at its refinery. The pre-feasibility study was completed by Engineers India Limited and the project is awaiting various approvals. RFQ for the DFR consultant is already out.
8Project Event: RFQ for Project Management Consultant is expected by April 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Apr/2018
8Release Date: May/2018
8Start Date: Q3:2018
8Completion Date: Q2:2022
Click here for more details.
8Project Name: Refinery shutdown project
8Project Cost: Rs 20 Crore
8Project Description: An existing company is planning for a 30-day shutdown of its Refinery. This is a planned maintenance shutdown
8Project Event: RFQ for Project Management Consultant is expected by February 2018.
8Project Event: RFQ for manpower is expected by February 2018.
8Expenditure Approval: Jan/2018
8RFQ Date: Feb/2018
8Release Date: Mar/2018
8Start Date: Apr/2018
8Completion Date: May/2018
Click here for more details.
8Project Name: Oil Field Development
8Project Cost: Rs 150 crore.
8Project Description: Promoter is planning the development of the Barsilla oilfield. The block was awarded to the company under the Discovered Small Fields Round 2016. Environment consultant has been hired as a consultant for PFR preparation. The project involves development drilling of oil wells and laying of an infield pipeline to connect with the nearest OIL's production facility (GGS). Currently, the project is in pre-clearance phase. Production from the block is expected to start by the end of 2021. Further RFQs are expected shortly.
8Project Event: RFQs for hiring Project Management Consultant is expected by March 2018.
8Expenditure Approval: Q4/2017
8RFQ Date: Mar/2018
8Release Date: Apr/2018
8Start Date: Q1/2019
8Completion Date: Q1/2021
Click here for more details

8Project Name:  Dual CNG-Diesel usage in rigs
8Project Cost: Rs 50 crore
8Project Description: Promoteris planning to power its own drilling rigs with Compressed Natural Gas (CNG) in addition to the already existing diesel mode. The project involves utilization of a dual fuel combustion system to power 19 diesel engines, which in turn would be used to run 5 drilling rigs. RFQs for the project have been slightly delayed. The CNG will be supplied from the GGS. Currently, dual fuel option is being tested on one engine. An EOI for Cascades, filling system, transportation and decanting had been floated from promoter's end. Further RFQs are expected shortly.
The mechanical equipment required would be Air Filter, Gas Mixer, Turbo Compressor, Gas Metering Control Unit, Knock Sensors, Dual Fuel Controller, Safety Valves, Controller, Common Rail System.
8Project Event: RFPs for transportation are expected by February 2018 instead of January 2018.
RFQs for hiring the mechanical equipment for Dual Fuel Combustion engine is expected by March 2018 instead of January 2018.
8Expenditure Approval: Oct/2017
8RFQ Date: Feb/2018
8Release Date: Mar/2018
8Start Date: May/2018
8Completion Date: Dec/2018
Click here for more information


**********************************