Software updates: Oil & gas projects
Jan 09: 8Project Name: Refinery Greenfield Ethylene Recovery Unit Project
8Project Cost: Rs 3800 Crore
8Project Description: An existing company along with EPCM contractor and licensor is carrying out engineering activities to construct an Ethylene Recovery Unit with a capacity of 332 KTPA at its refinery. RFQ for the equipment is already out.
8Project Event: RFQ for structural steelwork is expected by March 2018.
8Expenditure Approval: Q4:2016
8RFQ Date: Mar/2018
8Release Date: Apr/2018
8Start Date: Q3:2017
8Completion Date: Q3:2020
Click here for more detail.
8Project Name: Refinery BS-VI Diesel Hydrotreater Upgradation
8Project Cost: Rs 1100 Crore
8Project Description: An existing company along with EPCM contractor and licensor is planning to install a new Diesel Hydrotreater Unit (DHDT) of 1.9 MMTPA and a Hydrogen Generation (HGU) Unit of 22 KTPA to produce BS-VI High-Speed Diesel in its refinery. RFQ for the equipment is already out.
8Project Event: RFQ for civil and structural work is expected by March 2018.
8Expenditure Approval: Q1:2017
8RFQ Date: Mar/2018
8Release Date: Apr/2018
8Start Date: Q2:2018
8Completion Date: Q1:2020