Jan 08: 8Project Name: Refinery BS-VI Greenfield Project 8Project Cost: Rs 513 Crore 8Project Description: An existing company along with EPC contractor and licensor is planning to construct an IndselectG unit with a capacity of 80 KTPA to reduce sulphur from the indmax light gasoline and coker gasoline for making MS components to meet BS-VI MS pool specification at its refinery. RFQ for the equipment is already out. Tendering process for the equipment is going on. 8Project Event: RFQ for civil work is expected by March 2018. 8Expenditure Approval: Q3:2017 8RFQ Date: Mar/2018 8Release Date: Apr/2018 8Start Date: Q2:2018 8Completion Date: Q1:2021 Click here for more details. 8Project Name: Greenfield POL Terminal Project 8Project Cost: Rs 432 Crore 8Project Description: An existing company is planning to install a POL terminal with a capacity of 29170 KL. 8Project Event: RFQ for the consultant of preparing DFR is expected by February 2018. 8Expenditure Approval: Q3:2017 8RFQ Date: Feb/2018 8Release Date: Mar/2018 8Start Date: Q3:2018 8Completion Date: Q3:2020 Click here for more details. 8Project Name: Oil Field Development. 8Project Cost: Rs 200 crore. 8Project Description: Promoter is planning the development of an oilfield. The block was awarded to the company under the Discovered Small Fields Round 2016. The project involves development drilling of oil wells and laying of an infield pipeline to connect with the nearest production facility. Currently, the project is in pre-clearance phase. Production from the block is expected to start by the end of 2020. Further RFQs are expected shortly. 8Project Event: RFQs for hiring consultant for oilfield analysis is expected by Mar 2018. RFQs for hiring services for rigs and other oilfield services are expected by May 2018. 8Expenditure Approval: Q4/2017. 8RFQ Date: Mar/2018. 8Release Date: Apr/2018. 8Start Date: Q2/2019. 8Completion Date: Q4/2021. Click here for more details 8Project Name: Oil Field Development. 8Project Cost: Rs 500 crore 8Project Description: Promoteris planning the development of an offshore field block. The project involves drilling of oil wells, installation of one wellhead platform and laying of a pipeline. Currently, the project is in clearance stage. The whole project is expected to be executed by lump sum Integrated Project Mangement consultant through an Engineering Procurement Installation and commissioning model. A slight delay is expected in project RFQ. Further RFQs for the project are expected shortly. 8Project Event: RFQs for hiring IPM consultant and EPIC contractor are expected by March 2018. 8Expenditure Approval: Q2/2016. 8RFQ Date: Mar/2018. 8Release Date: Apr/2018. 8Start Date: Q2/2019. 8Completion Date: Q2/2021. Click here for more information