Jan 03: 8Project Name: Product Pipeline augmentation project
8Project Cost: Rs 277 Crore
8Project Description: An existing company along with EPC contractor is planning to augment its pipeline capacity to 6 MMTPA of petroleum products from the existing capacity 4.6 MMTPA. No additional land would be required for the project. Work is to be done in the existing stations only not in pipeline route. It includes replacement of 1 existing motor-driven Main Line Pumping Unit (MLPU), Replacement of 2 existing mainline pumps, Installation of 3 (2+1) motor-driven MLPUs.
8Project Event: RFQ for the listed equipment is to be expected by last week of February 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Feb/2018
8Release Date: Mar/2018
8Start Date: Q1:2018
8Completion Date: Q1:2020
Click here for more details.
8Project Name: POL Terminal Expansion Project
8Project Cost: Rs 108 Crore
8Project Description: An existing company is planning to expand its POL capacity from 82515 KL to 199725 KL by installing tanks with a capacity of 2 X 600 KL of ethanol, 4 X 25,000 KL of HSD, 1 X 12,000 KL of HSD and 1 X 4010 KL of HSD.
8Project Event: RFQ for the Project Management Consultant is expected by March 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Mar/2018
8Release Date: Apr/2018
8Start Date: Q2:2018
8Completion Date: Q1:2020
Click here for more details.
8Project Name: Oil Field Development
8Project Cost: Rs 150 crore.
8Project Description: Promoter is planning the development of an oil field. The block was awarded to the company under-discovered small fields round (DSF) in 2016. The project involves development drilling of 9 wells and laying of an infield pipeline to connect with the nearest production facility (GGS). Currently, the project is in pre-clearance phase. Production from the block is expected to start by the end of 2019. Further RFQs are expected shortly.
8Project Event: RFQs for hiring services for rigs and other oilfield services are expected by Mar 2018.
8Expenditure Approval: Q4/2017.
8RFQ Date: Mar/2018.
8Release Date: Apr/2018.
8Start Date: Q4/2018.
8Completion Date: Q2/2020.
Click here for more details

8Project Name: Oil Field Development.
8Project Cost: Rs 300 crore
8Project Description: Promoteris planning development drilling of 6 wells to augment production from an oil field. The project would also involve the conversion of 3 exploratory wells into development wells, up-gradation of the GCS and laying of an infield pipeline. The project is in the pre-clearance phase. RFQ for the project can be expected shortly.
8Project Event: RFQ for hiring EPC contractor for GCS and pipelines is expected by Mar 2018.
8Expenditure Approval: Q3/2016.
8RFQ Date: Mar/2018.
8Release Date: Apr/2018.
8Start Date: Q3/2018.
8Completion Date: Q4/2020.