Software Updates : Power Projects
Dec 29: 8Project Name: Hydroelectric Plant (Unit - 1) Maintenance Project
8Project Cost: 20 crores
8Project Description: The owner has planned a 20-day scheduled maintenance of Unit-1 (165 MW) in the 990 MW (6*165) Hydroelectric Station covering annual inspection and overhaul of equipment which includes overhauling and checking of auxiliary parts of the turbine-generator set, bearing sets, level gauge, sensors and seals.
8Equipment required will be turbine bearings, gland seals, pipes, guide vanes seal, spiral casing, spiral drain valve, foundation parts, change of worn out bushes of guide vanes journals, among others.
8Project Event: RFQs for equipment are expected by third week of January 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: 22/Jan/2018
8Release Date: Feb/2018
8Start Date: 5/Mar/2018
8Completion Date: 24/Mar/2018
Click here for more information
8Project Name: Greenfield Thermal Power Plant
8Project Cost: 7000 crores
8Project Description: The owner along with EPC contractor is setting up a 1080 MW (4*270 MW) greenfield Thermal Power Plant. EC was granted to this project on March 15, 2017. At present, civil construction activities are ongoing.  has already floated tenders to procure long lead items like ESP (Electrostatic Precipitators) and transportation of boiler drum. Further tenders regarding erection and commissioning, transportation services and control and instrumentation (C&I) equipment have been released and are currently under scrutiny. The progress of works has been hampered due to heavy rains in the plant area. Now, RFQs for electrical equipment and FGD equipment are expected shortly.
8Project Event: RFQs for electrical equipment and FGD equipment are expected in February 2018.
8Expenditure Approval: Apr/2014
8RFQ Date: Feb/2018
8Release Date: Mar/2018
8Start Date: Dec/2017
8Completion Date: Nov/2024
Click here for more information

**********************************