Dec 28: 8Project Name: Hydroelectric Plant (Unit - 3) Maintenance Project
8Project Cost: 11 crores
8Project Description: The owner has planned a 7-day scheduled maintenance of Unit-3 (28.94 MW) in the 77.34 MW Hydroelectric Station, covering annual inspection and overhaul of equipment which includes overhauling and R&M works of auxiliary parts of the turbine-generator set, bearing sets and seals.
8Equipment required will be turbine bearings, gland seals, pipes, guide vanes seal, spiral casing, spiral drain valve, fasteners, among others.
8Project Event: RFQs for equipment are expected by first week of January 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: 20/Jan/2018
8Release Date: Feb/2018
8Start Date: 19/Mar/2018
8Completion Date: 25/Mar/2018
Click here for more information
8Project Name: Renovation and Modernisation of ash slurry disposal system in Thermal Power Station
8Project Cost: 6 crores
8Project Description: The owner is planning to renovate and modernize its ash slurry disposal system for unit 1, 2 and 3 in the 1050 MW (5*210 MW) Thermal Power Station. The design capacity of the present pumps contains 19% ash content, whereas the coal now being used contains ash content of 40 to 45%. Due to this the height of the ash dyke and the length of the discharge pipe line has been increased but the existing arrangement is not advisable for the long term due to its proximity to the cooling water outlet channel. The owner will now renovate and modernize the existing ash slurry disposal system for long term needs, and the project is under proposal stage for obtaining administrative approval.
8Project Event: RFQ for R&M of ash slurry disposal system is expected by February 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Feb/2018
8Release Date: Mar/2018
8Start Date: Apr/2018
8Completion Date: Jun/2018
Click here for more information

**********************************