Dec 27: 8Project Name: Refinery Expansion Project 8Project Cost: Rs 27000 Crore 8Project Description: An existing company is planning to expand its existing 1 MMTPA refinery to 10 MMTPA by installing new 9 MMTPA crude distillation unit at its refinery. The pre-feasibility study was completed by Engineers India Limited and the project is awaiting various approvals. 8Project Event: RFQ for hiring DFR consultant is expected by January 2018. 8Expenditure Approval: Q3:2017 8RFQ Date: Jan/2018 8Release Date: Feb/2018 8Start Date: Q3:2018 8Completion Date: Q2:2022 Click here for more details. 8Project Name: LPG Bottling Plant Greenfield Project 8Project Cost: Rs 116 Crore 8Project Description: An existing company along with EPC contractor is carrying out the engineering activities to install an LPG bottling plant with a capacity of 120 TMTPA by constructing 3 X 350 MT mounded storage vessels. At present civil work is going on. 8Project Event: RFQ for erection and installation work is expected by March 2018. 8Expenditure Approval: Q2:2017 8RFQ Date: Mar/2018 8Release Date: Apr/2018 8Start Date: Q3:2017 8Completion Date: Q2:2019 Click here for more details. 8Project Name: Oil Field Development 8Project Cost: Rs 150 crore. 8Project Description: Promoter is planning development of an Oil Field. The block had been awarded to the company in Discovered Small Fields round in 2016. Currently, the project is in pre-planning stage. The company is in process of carrying out oil and gas field study so as to estimate the possible oil reserve. Further RFQs for the project are expected shortly. 8Project Event: RFQs for hiring various oil and gas services is expected by Q1 2019. 8Expenditure Approval: Q2/2018. 8RFQ Date: Q1/2019. 8Release Date: Q2/2019. 8Start Date: Q4/2019. 8Completion Date: Q4/2021. Click here for more details 8Project Name: Greenfield Early Production System Development. 8Project Cost: Rs 250 crore. 8Project Description: Promoter has proposed to set up an Early Production System. The project would also involve laying of a pipeline to the GGS from the oilfield. The proposed facilities in this project are: HP Separator Skid, CO2 and Moisture Removal Skid, Dew Point Depression Skid, N2 Based Skid, Produced Water Storage and Bay Facilities and Other Utilities and Offsites. The equipment requirement will be Gas Turbine, Air Compressor, Storage tanks, Well Head, Water Injection Well, Flare Stack,Gas pipeline. 8Project Event: RFQ for the civil works can be expected by Q2, 2018 instead of January 2018. RFQ for equipment is expected by Q2 end 2018. 8Expenditure Approval: Q2/2016. 8RFQ Date: Apr/2018 8Release Date: May/2018 8Start Date: Q2/2018 8Completion Date: Q3/2019 Click here for more information