Software Updates : Power Projects
Dec 22: 8Project Name: Hydro Power Station Maintenance Project (Unit - 3)
8Project Cost: 16 crores
8Project Description: The owner  has planned a 20-day scheduled maintenance of Unit-3 (157 MW) in the 785 MW Hydro Power Station covering annual inspection and overhaul of equipment which includes overhauling of auxiliary parts of the turbine-generator set, bearing sets, seals, governor and oil cooling unit.
8Equipment required will be turbine bearings, gland seals, pipes, guide vanes seal, spiral casing, spiral drain valve, among others.
8Project Event: RFQs for equipment are expected by first week of January 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: 5/Jan/2018
8Release Date: 28/Jan/2018
8Start Date: 20/Feb/2018
8Completion Date: 11/Mar/2018
Click here for more information
8Project Name: Thermal Power Plant - FGD Addition
8Project Cost: 300 crores
8Project Description: The owner is scheduled to install an FGD for a 600 MW super-critical thermal power complex. The company is expected to float tenders for the same. At present, feasibility studies are ongoing by the owner. The project start date is slated for early 2020. RFQ for supply of FGD is expected to be out by Q3 of 2018. The major requirements will be FGD, stacker- reclaimer, earthwork, cranes, pipes, installation, gypsum disposal, wet lime among others.
8Project Event: RFQ for supply of FGD is expected to be out by the Q3 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Q3:2018
8Release Date: Q1:2019
8Start Date: Q1:2020
8Completion Date: Q2:2022
Click here for more information

**********************************