Dec 20: 8Project Name: Onshore Field Development 8Project Cost: Rs 100 crore. 8Project Description: Promoter is planning the development of an oil field. The block, along with two other blocks had been awarded to the company in small fields bid round 2016. The company is planning a study of the field prior to starting production. A detailed study of the oil field to estimate possible reserves and production is expected shortly. Currently, the manpower hiring process is going on there in the project for various roles. Moreover, an EOI is also expected for various drilling services. Further RFQs are expected shortly. 8Project Event: RFQ for hiring consultant for oil field studies and analysis is rescheduled to January 2018. RFQ for EOI for various oil and gas services is expected by Q1 2018. 8Expenditure Approval: Q3/2017. 8RFQ Date: 25/Jan/2018. 8Release Date: Feb/2018. 8Start Date: Apr/2018. 8Completion Date: Apr/2019. Click here for more details 8Project Name: Early Production System 8Project Description: Promoteris planning an Early Production System. The project involves the construction of an EPS and laying of a pipeline for crude evacuation. The following units have been proposed in the facility: Production field headers & test headers, Group separator, Gas scrubber, Bath heater, Dispatch pump, Flare System, Orifice meter, Mass flow meter, Tube well, Firefighting system, DG set. Further RFQs are expected shortly. 8Project Event: RFQ for the hiring EPC contractor is expected by January 2018 instead of December end 2017. 8Expenditure Approval: Q4/2016 8RFQ Date: 25/Jan/2018. 8Release Date: Q1/2018 8Start Date: Jun/2018 8Completion Date: Q1/2019 Click here for more information 8Project Name: Refinery BS VI Motor Spirit Block Upgradation 8Project Cost: Rs 3313 Crore 8Project Description: An existing company along with EPC contractor is carrying out engineering activities to upgrade the BS V Motor spirit block to BS VI Motor Spirit block at its refinery, Kerala involving the construction of a Naphtha hydrotreater unit, Continuous catalytic reformer (CCR) unit, and a Light naphtha isomerization unit. Procurement for the CCR unit is already completed. 8Project Event: RFQ for the procurement for naphtha hydrotreater unit and light naphtha isomerization unit is expected by January 2018. 8Expenditure Approval: Q4:2016 8RFQ Date: Jan/2018 8Release Date: Mar/2018 8Start Date: Q4:2016 8Completion Date: Q2:2020 Click here for more details. 8Project Name: Greenfield POL Terminal Project 8Project Cost: Rs 140 Crore 8Project Description: An existing company along with EPC contractor is planning to construct a POL terminal with a capacity of 24458 KL. 8Project Event: RFQ for equipment is to be expected by January 2018. 8Expenditure Approval: Q2:2017 8RFQ Date: Jan/2018 8Release Date: Feb/2018 8Start Date: Q1:2018 8Completion Date: Q1:2020 Click here for more details.