Software Updates : Power Projects
Dec 19: 8Project Name: Combined Cycle Power Plant (GT-4) Maintenance Project
8Project Cost: 20 crores
8Project Description: The owner has planned a 10-day scheduled maintenance of Unit-4 Gas Turbine (250 MW) in the 1500 MW ( 4*250 MW GT + 2*250 MW ST) combined gas based power station covering major combustion inspection and overhauling of equipment which includes overhauling of auxiliary parts of the gas turbine set and change out the fuel nozzles and to check out combustion liners and crossfire tubes. Equipment required will be fuel nozzles, combustion liners, crossfire tubes, buckets, transition pieces, casing, spark plug assembly, among others.
8Project Event: RFQ for equipment is expected in mid-January 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: Jan/2018
8Release Date: Feb/2018
8Start Date: 10/Mar/2018
8Completion Date: 19/Mar/2018
Click here for more information
8Project Name: Thermal Power Station - FGD Addition
8Project Cost: 900 crores
8Project Description: The developer is planning the installation of a Flue Gas Desulphurization (FGD) unit and retrofitting it's ESP at it's 1170 MW (3*250 + 2*210 MW) Thermal Power Station. The company is expected to float tenders for the same. Currently the 1170 MW power complex is under shut down due to low schedule and site survey activities are ongoing for a feasibility report for the FGD for submission to CEA for approval. Work on the project is meant to start in early 2021. RFQ for supply of FGD is expected to be out by Q1 2019.
8The major requirements will be FGD, stacker and reclaimer, earthwork, cranes, pipes, installation, gypsum disposal, wet limestone, among others.
8Project Event: RFQ for equipment is expected in mid-January 2018.
8Expenditure Approval: Q2:2018
8RFQ Date: Q1:2019
8Release Date: Q3:2019
8Start Date: Q1:2021
8Completion Date: Q2:2023