Dec 18: 8Project Name: Offshore Field Development.
8Project Cost: Rs 540 crore.
8Project Description: Promoter is planning the development of an offshore field, which is a part of the Western Offshore region, by drilling of new wells and installation of a new well-head platform with associated pipelines and modification of the two existing platforms. An overall production of 0.5 MMT of oil and 0.7 BCM of gas is envisaged from the project. The oil and gas from this project will be evacuated to promoter’s onshore terminals. Further RFQs for the project are expected shortly.
8Project Event: RFQ for hiring an EPC contractor for platform installation and pipeline is expected by November end 2017.
8Expenditure Approval: 23/Feb/2017.
8RFQ Date: Jan/2018    .
8Release Date: Q1/2018.
8Start Date: Q1/2018.
8Completion Date: Nov/2019.
Click here for more details

8Project Name: Offshore Field Development
8Project Cost: Rs 510 crore
8Project Description: Promoteris planning the development of the offshore block located in the Western Offshore. The project envisages a peak oil production of 1,000 bopd, peak condensate production of 1,800 bcpd and a peak gas production of 0.3 MMSCMD. The cumulative oil production of 0.2 MMT, cumulative condensate production of 0.4 MMT and the cumulative gas production of 0.6 BCM is envisaged during the life of the project.
Following developments have been proposed for the project: Creation of facilities in the form of one new slot wellhead platform along with associated pipeline, topside modification of two existing process platforms and drilling of two wells. RFQs for the project are expected shortly.
8Project Event: RFQs for hiring an EPC contractor for wellhead platform and pipelines is expected by January 2018.
8Expenditure Approval: Feb/2017
8RFQ Date: Jan/2018
8Release Date: Q1/2018
8Start Date: Q2/2018
8Completion Date: Nov/2019
Click here for more information
8Project Name: Greenfield 2G Ethanol Bio- Refinery
8Project Cost: Rs 750 Crore
8Project Description: An existing company along with the licensor is planning to construct an ethanol plant based on the DBT-ICT 2G Ethanol technology developed indigenously to produce 100 KL fuel-grade ethanol per day, primarily from biomass and will use approximately 72 MTPD of biomass per year. PMC consultant has been hired.
8Project Event: RFQ for equipment is expected by January 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: Jan/2018
8Release Date: Mar/2018
8Start Date: Q1:2018
8Completion Date: Q1:2019
Click here for more details.
8Project Name: Refinery Propylene Recovery Unit Expansion Project
8Project Cost: Rs 3150 Crore
8Project Description: An existing company along with the EPC contractor and the licensor is carrying out engineering activities on a propylene recovery unit with a capacity of 700,000 MTPA to produce Propylene at its Refinery. Equipment and services needed for the project have already been ordered. At present, mechanical work is going on.
8Project Event: RFQ for Commissioning and Pre-commissioning activities is expected by February 2018.
8Expenditure Approval: Q2:2015
8RFQ Date: Feb/2018
8Release Date: Mar/2018
8Start Date: Q3:2015
8Completion Date: Q3:2018