Dec 14: 8Project Name: Hydroelectric Plant Maintenance Project (Unit- 4) 8Project Cost: 20 crores 8Project Description: The owner has planned a 40-day scheduled maintenance of Unit-4 (115 MW) in the 690 MW (6*115 MW) Hydro Power Station covering annual inspection and overhaul of equipment which includes overhauling of auxiliary parts of the turbo-generator set, bearing sets, seals, governor and oil leakage unit, rotor assembly. 8Equipment required will be turbine guide bearings,vacuum breaking valve, pipes, air seals, water seals, cleaning of field winding, fabrication of platform in the draft tube for inspection of runner, among others. 8Project Event: RFQs for equipment required are expected by fourth week of December 2017. 8Expenditure Approval: Q2:2017 8RFQ Date: 28/Dec/2017 8Release Date: 10/Jan/2017 8Start Date: 29/Jan/2018 8Completion Date: 9/Mar/2018 Click here for more information 8Project Name: Pumped Storage Greenfield Plant 8Project Cost: 1000 crores 8Project Description: A Joint Venture is planning to construct a greenfield 400 MW pumped storage scheme which envisages re-circulating the water between lower and upper reservoirs. TOR is yet to be granted. Currently, the owner is carrying out the project scoping activities with the Government of Maharashtra. The owner will come out with a bid for S&I activities and DPR preparation. 8Project Event: RFQ for S&I and DPR preparation is expected by Q2 2018. 8Expenditure Approval: Q1:2018 8RFQ Date: Q2:2018 8Release Date: Q3:2018 8Start Date: Q2:2021 8Completion Date: Q4:2025 Click here for more information