Dec 13: Ammonia-Urea & Captive Power Unit Greenfield Project 8Cost - Rs 7000 Crore 8Project Description: A Fertilizer Company is awaiting environmental clearance for its greenfield ammonia-urea unit with a capacity of 2x2500 MTPD of ammonia, 4000 MTPD of urea and 2x 150 MW of Captive power unit at in India. The plant will be attached to an FRSU based terminal.The equipment requirements are Compressors, Turbines, Exchangers, Vaporizers, Subcoolers, Filters, Pumps, Heaters, Towers, Vessels, Storage systems, Cooler, Furnaces, Stacks, Converters, Boilers, Drums, Blowers, Economizers, Preheaters, Reactors, Tanks, Reactors, Evaporators, Condensers, Separators, Ejectors, Absorbers, Prilling towers, Absorbers, Heat exchangers, Columns, Generators Coal handling plant (CHP), Ash handling plant (AHP), Switchyard, Control and instrumentation equipment, Transmission lines, Substation, Transformers 8Project Event: The tender has already been released for Engineering Consultant in November 2017 and finalization is due in Q1 2018. The tender for equipment is likely to be released in Q1 2018. Click here for more information DAP/NPK- Phosphoric Acid & Sulphuric Acid Greenfield Project 8Cost - Rs 2000 Crore Project Description: A Fertilizer company is awaiting environmental clearance for its greenfield DAP/NPK unit with a capacity of 6000 MTPD of DAP/NPK, 3000 MTPD of Phosphoric Acid and 4500 MTPD of Sulphuric Acid Unit in India. The equipment requirements are Steam Turbine Generators, Economizers, Reheaters, Boilers, Sulphur Combustor, Drying Towers, Vapor Separators, Converters, Absorbers, Absorber Exchangers, Sulphur filters, Sulphuric Melting Tank, Motors, Pumps, Storage Systems, Soda Ash Silos, Rotary Dryers, Grinding Unit, Ball Mill, Mixing Tanks, Blending Unit, Wet Scrubber Unit, Venturi Scrubber Unit, Cyclone System, Air Pollution Control System, Vibro Shifter and more 8Project Event: RFQ for Project Management Consultant is likely to be released in March 2018, The tender for LSTK contractor is likely to be released in Q2 2018 Click here for more information SSP/Sulphuric Acid Annual Maintenance Project 8Cost - Rs 0.35 Crore 8Project Description: A Fertilizer Company is planning an annual shutdown maintenance in April 2018 at their existing fertilizer complex in India. The existing capacity is made up of 120000 MTPA of SSP and 79000 MTPA of Sulphuric Acid. Pre-Vendor Qualification may be necessary for a maintenance contractor. Project Event: RFQ for a maintenance contractor is likely to be released in Q1 2018 Click here for more information Those subscribing to our petroleum portal may not have access to these items. Please contact our marketing department for access.