Dec 13: 8Project Name: Refinery Maintenance Project 8Project Cost: Rs 20 Crore 8Project Description: An existing company along with EPC contractor is planning to overhaul its 300,000 barrels per day, refinery for about 45 days in the month of March-April 2018. The company had earlier planned to shut the refinery for 20 days in the month of November-December 2017 but that had to be deferred. 8Project Event: RFQ for manpower is expected by last week of December 2017 8Expenditure Approval: Q2:2017 8RFQ Date: Dec/2017 8Release Date: Jan/2018 8Start Date: Feb:2018 8Completion Date : Apr:2018 Click here for more details. 8Project Name: Floating Storage & Regasification LNG Terminal Greenfield Project 8Project Cost: Rs 1200 Crore 8Project Description: An existing company along with EPC contractor is carrying out construction activities to install a 4 MMTPA Floating Storage & Regasification LNG Terminal. At present mechanical work is going on. 8Project Event: RFQ for commissioning and pre-commissioning work is expected by February 2018. 8Expenditure Approval : Q4:2014 8RFQ Date : Feb/2018 8Release Date: Mar/2018 8Start Date: Q1:2015 8Completion Date: Jul:2018 Click here for more details. 8Project Name: Offshore Field Development. 8Project Cost: Rs 500 crore. 8Project Description: Promoter is planning the development of the Offshore Field. The project involves drilling of oil wells, installation of one wellhead platform and laying of pipeline. Currently, the project is in clearance stage. The whole project is expected to be executed by lump sum Integrated Project Mangement consultant and Engineering Procurement Installation and commisioning model. Further RFQs for the project are expected shortly. 8Project Event: RFQs for hiring IPM consultant and EPIC contractor is expected by Q1, 2018. 8Expenditure Approval: Q2/2016. 8RFQ Date: Q1/2018. 8Release Date: Q2/2018. 8Start Date: Q2/2019. 8Completion Date: Q2/2021. Click here for more details 8Project Name: CBM Block Development 8Project Cost: Rs 447 crore 8Project Description: Promoter is planning the development of the CBM Block by drilling a total of 68 wells. An overall quantity of 0.3 MMSCMD of gas has been envisaged to be produced from the project. Promoter, in turn, has selected a US firm, to carry out the feasibility study for the project. Further RFQ's for the project are expected shortly. 8Project Event: EOI from promoter for drilling rigs as well as various mechanical and electrical equipment are expected by January 2018. 8Expenditure Approval: Q1/2016 8RFQ Date: Jan/2018 8Release Date: Feb/2018 8Start Date: Q3/2018 8Completion Date: Q3/2021 Click here for more information