Dec 04: 8Project Name: Combined Cycle Power Station Maintenance Project (GT - 2) 8Project Cost: Rs 16 crore 8Project Description: The owner has planned a 28-day scheduled maintenance of Unit-2 Gas Turbine (250 MW) in the 1500 MW ( 4*250 MW GT + 2*250 MW ST) combined gas based power station covering major inspection and overhauling (type C) of equipment which includes overhauling of auxiliary parts of the gas turbine set and generator set. Equipment required will be air filters, nozzle, water and oil piping, buckets, shrouds, support rings, combustion liners, thrust bearings, casings, seals, generator protection relay, inspect the fuel system and lubrication of generator, among others. 8Project Event: RFQ for equipment is expected in third week of December 2017. 8Expenditure Approval: Q3:2016 8RFQ Date: 20/Dec/2017 8Release Date: Jan/2018 8Start Date: 1/Feb/2018 8Completion Date: 28/Feb/2018 Click here for more information 8Project Name: Thermal Power Station - FGD Addition 8Project Cost: Rs 300 crore 8Project Description: The proponent is scheduled to install FGDs for Units 1 and 2 at it's 600 MW (2*300 MW) thermal power plant. At present, feasibility studies and phasing plans are underway. The project is expected to kick off in late 2021. RFQs for supply of FGDs are expected to be out by the Q3 2018. Interested parties are advised to go through the vendor registration process with the owner. 8The major requirement will be FGDs, stacker and reclaimer, earth work, cranes, pipes, installation, gypsum disposal, wet lime among others. 8Project Event: RFQs for supply of FGDs are expected in Q3 2018. 8Expenditure Approval: Q1:2018 8RFQ Date: Q3:2018 8Release Date: Q4:2018 8Start Date: Q4:2021 8Completion Date: Q1:2023 Click here for more information 8Project Name:500 MW Solar PV Grid Project 8Project Cost: Rs 3000 crore 8Project Description: The proponent is planning to construct a 500 MW solar PV grid connected plant. The project is still under planning and site surveys are going on for scoping of the project. The project is under consideration of the Madhya Pradesh Government and after appraisal, bids for solar tariff rates is likely to be elicit. 8Project Event: RFQ for a power purchase auction is expected in Sep 2019. 8Expenditure Approval: Q3:2018 8RFQ Date:Sep/2019 8Release Date: Q4:2019 8Start Date: Q3:2020 8Completion Date:Q4:2021 Click here for more information