Nov 27: 8Project Name: Brownfiled Thermal Power Station 8Project Cost: Rs 4000 crore 8Project Description: The owner along with an environmental consultant is carrying out the clearance activities for scoping the environment clearance for a 660 MW brownfield lignite based super-critical thermal power plant at the existing premises of 1080 MW thermal power complex. TOR has been accorded on 25 February 2015. Draft EIA report has been submitted to Rajasthan SPCB for organizing the public hearing which was conducted on 23 July 2015. The coal linkage factor is an area of concern due to which the project is getting delayed which is expected to elicit by Q2 2018. The power generated is supplied to the Government of Rajasthan Discoms through PPA. Work at the site is expected to kick off by Q3 2019. The owner will come out with an EPC (turnkey) package after getting EC. 8Project Event: RFQ for an EPC (turnkey) contractor is expected by Q4 2018. 8Expenditure Approval: Q4:2016 8RFQ Date: Q4:2018 8Release Date: Q1:2019 8Start Date: Q3:2019 8Completion Date: Q1:2024 Click here for more information 8Project Name: Hydro Power Station Maintenance Project (Unit - 2) 8Project Cost: Rs 17 crore 8Project Description: The owner has planned a 28-day scheduled maintenance of Unit-2 (12 MW) in the 48 MW (4*12 MW) hydro power station covering annual inspection and overhaul of equipment which includes overhauling of auxiliary parts of the oil bearing sets, turbine sets, seals, governor and transformer auxiliaries, polishing of the various under water parts of the turbines, stator & rotor winding of the generator. 8Equipment required will be turbine bearings, gland seals, pipes, air seals, spiral casing, pressure relief valve, checking and replacing of transformer auxiliary parts, nozzles, cleaning of field winding of stator and rotor of generator, among others. 8Project Event: RFQs for equipment are expected by second week of December 2017. 8Expenditure Approval: Q2:2017 8RFQ Date: 10/Dec/2017 8Release Date: 26/Dec/2017 8Start Date: 1/Feb/2018 8Completion Date: 28/Feb/2018 Click here for more information