Nov 20: 8Project Name: Greenfield Hydroelectric Power Station 8Project Cost: Rs 2700 crore 8Project Description: The owner is planning to construct a 330 MW (3*110 MW) greenfield hydroelectric power station. Survey work for the site and geological mapping for the dam site has been completed. Investigations for DPR preparation is underway at present. Currently, hydro-logical studies, geographical studies are in progress and are expected to be completed by November 2017. The owner will come out with an NIT for drilling and drifting. The owner will also come with an RFQ for a DPR consultant soon. 8Project Event: RFQ for drilling and drifting is expected by fourth week of November 2017. 8Expenditure Approval: 2017 8RFQ Date: 25/Nov/2017 8Release Date: Dec/2017 8Start Date: Q2:2020 8Completion Date: Q3:2025 Click here for more information 8Project Name: Thermal Power Station - FGD Addition 8Project Cost: Rs 400 crore 8Project Description: The developer is scheduled to install an FGD and retrofitting of ESP for a 500 MW unit out of its 2600 MW (3x200 + 3x500 MW) thermal power plant. The company is expected to float tenders for the same. At present, site survey activities are ongoing. The project is expected to kick off in late 2022. RFQ for supply of FGD are expected to be out by the second quarter of 2019. The major requirement will be FGD, stacker and reclaimer, earthwork, cranes, pipes, installation, gypsum disposal, wet lime among others. 8Project Event: RFQ for supply of FGD and retrofitting of ESP are expected to be out by the Q2 2019. 8Expenditure Approval: Q4:2016 8RFQ Date: Q2:2019 8Release Date: Q3:2019 8Start Date: Q4:2022 8Completion Date: Q2:2024 Click here for more information 8Project Name: Thermal Power Station Maintenance Project (Unit - 1) 8Project Cost: Rs 11 crore 8Project Description: The owner has planned an 8-day scheduled maintenance of Unit-1 (135 MW) in the 1080 MW Thermal Power Station covering maintenance and inspection of equipment comprising of boiler refractories, valves, piping, inspection of oil in boiler and refilling it, seals, among others. 8Project Event: RFQ for equipment is expected by the fourth week of December 2017. 8Expenditure Approval: Q2:2017 8RFQ Date: 20/Dec/2017 8Release Date: Jan/2018 8Start Date: 7/Mar/2018 8Completion Date: 14/Mar/2018 Click here for more information