Software Updates : Power Projects
Nov 15: 8Project Name: Brownfield Thermal Power Plant Expansion
8Project Cost: Rs 4000 crore
8Project Description: The owner along with EPC Contractor is carrying out basic engineering activities for a brownfield 660 MW Supercritical Plant at the Thermal Power Station. The power station had two 2x105 MW units which are under shutdown. The EPC contractor will itself carry out procurements for Boiler and Turbine in which auxiliaries for Boiler and Turbine will come from the contractor while I.D. Fan, F.D. Fan, civil works, BOP package and erection and commissioning will be done by subcontractors. Currently, the owner has not awarded LOA to the EPC contractor due to financial crunch by the owner's side as there are already two ongoing projects of the developer. LOA is expected to be elicited by March 2018. The EPC contractor will come out with civil and BoP package after LOA has been awarded.
8Project Event: RFQs for civil works and transportation services are expected by Q2 2018.
8Expenditure Approval: May/2015
8RFQ Date: Q2:2018
8Release Date: Q3:2018
8Start Date: Q1:2019
8Completion Date: Q3:2023
Click here for more information
8Project Name: Thermal Power Station - Dismantling 
8Project Cost: Rs 60 crore
8Project Description: The owner is planning to retire and dismantle Units 1 and 2 (2*120 MW) of it's 1350 MW (2*210 + 2*200 + 1*210 + 1*500 MW) of the thermal power plant. At present, the consultant is working on a feasibility study. As of now, the units have been in shut down since July, 2016 due to low schedule. RFQs for civil work and dismantling services of various equipment are expected by the 1st quarter of 2018. The dismantling work is likely to begin by May 2018.
8The major requirement will be cranes, dozers, dismantling services for electrical, mechanical and control and instrumentation (C&I) equipment, onsite inspection, inventorying, segregation and estimation among others.
8Project Event: RFQ for dismantling services of various equipment is expected by Q1 2018.
8Expenditure Approval: Q3:2017
8RFQ Date: Q1:2018
8Release Date: Q2:2018
8Start Date: Q2:2018
8Completion Date: Q4:2019
Click here for more information

**********************************