Nov 15: 8Project Name: Early Production System
8Project Cost: Rs 30 crore
8Project Description: Promoter is planning setting up of an EPS (Early Production System) in  Andhra Pradesh. The project will involve supply as well as the installation of the Early Production System. The project will involve supply as well as the installation of an Early Production System around 4 wells drilled in the oilfield. Eventually, there are plans for drilling of 20 more wells by the year 2019. An overall investment of 750 million US dollars had been earmarked for the development of the entire oilfield.
8Project Event: RFQ for hiring the EPC contractor is expected by Q1 2018.
8Expenditure Approval: Nov/2017.
8RFQ Date: Q1/2018.
8Release Date: Q1/2018.
8Start Date: Q2/2018.
8Completion Date: Q2/2019.
Click here for more information
8Project Name: Refinery Propylene Recovery Unit Expansion Project
8Project Cost: Rs 3150 Crore
8Project Description: An existing company along with EPC contractor and Licensor Spheripol Technology from Basell, Italy is carrying out engineering activities on a propylene recovery unit with a capacity of 700,000 MTPA to produce Propylene at its Refinery. equipment and services needed for the project have already been ordered.
8Project Event: RFQ for Erection and Installation work is expected by December 2017.
8Expenditure Approval: Q2:2015
8RFQ Date: Dec/2017
8Release Date: Jan/2018
8Start Date: Q3:2015
8Completion Date: Q3:2018
Click here for more details.
8Project Name: LPG Bottling Plant Expansion Project
8Project Cost: Rs 161 Crore
8Project Description: An existing company is planning to expand its existing capacity from 1000 MTPA to 2800 MTPA in the LPG bottling plant. Environmental Clearance is expected by April 2018.
8Project Event: RFQ for listed equipment is expected by January 2018.
8Expenditure Approval: Q2:2017
8RFQ Date: Jan/2018
8Release Date: Feb/2018
8Start Date: Q2:2018
8Completion Date: Q2:2029