Software Updates : Power Projects
Nov 14: 8Project Name: Greenfield Thermal Power Project
8Project Cost: Rs 8000 crore
8Project Description: The owner is carrying out the basic engineering activities for the 1320 MW (2*660 MW) greenfield super-critical thermal power plant. The owner has selected an EPC contractor on 22 December 2016. Currently piling work is going on at the site. BTG package will be provided by the EPC contractor. The EPC contractor will float a BoP package which includes CHP, switchyard, ash handling plant, cooling tower, chimney, fire protection system, raw water system among others.
8Project Event: RFQs for BoP package are expected by Q1 2018.
8Expenditure Approval: Q4:2016
8RFQ Date: Q1:2018
8Release Date: Q2:2018
8Start Date: Q2:2017
8Completion Date: Q4:2021
Click here for more information
8Project Name: Thermal Power Station Maintenance Project (Unit - 4)
8Project Cost: Rs 16 crore
8Project Description: The developer is planning to carry out maintenance activities at its Unit - 4 (200 MW) out of 850 MW (2*120+2*200+1*210+1*500 MW) Thermal Power Station. The activities are expected to begin by the start of March 2018. RFQs for inspection and various short lead items required in an annual overhaul are expected shortly.
8 The requirement will include tubes, buckstays, relay, bearings and inspection services, air filters, nozzle, boiler tubes, valves, journal bearings, pipes, casing, among others.
8Project Event: RFQ for maintenance equipment is expected in mid December 2017.
8Expenditure Approval: Q2:2017
8RFQ Date: 13/Dec/2017
8Release Date: Jan/2018
8Start Date: 1/Mar/2018
8Completion Date: 21/Mar/2018
Click here for more information

**********************************