Software updates: Fertilizer projects
Nov 10: Ammonia-Urea Energy Saving Project
 
8Cost - Rs 347 Crore
 
8Project Description: A Fertilizer company is planning to reduce the energy consumption of Ammonia and Urea units from 8.20 Gcal/MT to 7.70 Gcal/MT and 5.79 Gcal/MT to 5.33 Gcal/MT respectively In India. The capacity of the ammonia plant is 3500 MTPD and the urea capacity is 6060 MTPD. There is also as 30 MW of Captive Power Plant in the complex. The equipment requirements are Process Air Compressor (PAC), Gas Turbine, Heat Recovery Steam Generation, Pumps, Pipes, among others
 
8Project Event: Expression Of Interest (EOI) has been out for an LSTK contractor in November 2017.
 Click here for more information or EOI for more
 NPK/SSP Annual Maintenance Project  
 
8Cost - Rs 0.30 Crore
 
8Project Description: A Fertilizer company is planning an annual maintenance shutdown in March or April 2018 at their existing fertilizer complex In India. The existing capacity is made up of 132000 MTPA of SSP, 30000 MTPA of NPK Fertilizer. Pre-Vendor Qualification may be necessary for a maintenance contractor.
 
8Project Event: RFQs for the Annual Maintenance Contractor is likely to be released in January or February 2018.
 Click here for more information
 
NPK Fertilizer Annual Maintenance Project 
 
8Cost - Rs 0.15 Crore
 
8Project Description: A Fertilizer company is planning an annual maintenance shutdown in May or June 2018 at their existing fertilizer complex In India. The existing capacity is made up of 42000 MTPA of NPK. Pre-Vendor Qualification may be necessary for a maintenance contractor.
 
8Project Event: RFQs for the Annual Maintenance Contractor is likely to be released in February or March 2018
 Click here for more information


**********************************