Software Updates : Power Projects
Nov 09: 8Project Name: Greenfield Hydroelectric Project
8Project Cost: Rs 300 crore
8Project Description: The owner along with an EIA consultant is carrying out the scoping for  environment clearance for a 48 MW (3*16 MW) greenfield hydel power project. The project is a downstream development of Hydroelectric Project (180 MW). Currently forest clearance (Stage-1) has been accorded for diversion of forest land. The Asian Development Bank (ADB) has agreed in principle to finance the project. The owner will come out with an Expression of Interest for civil works costing Rs 229. 35 crores soon following the HM and E&M works in a gap of a month.
8Project Event: RFQ for civil works are expected by Q1 2018 and award of work is expected by the following 4-5 months.
8Expenditure Approval: Q3:2017
8RFQ Date: Q1:2018
8Release Date: Q2:2018
8Start Date: Q4:2018
8Completion Date: Q4:2022
Click here for more information
8Project Name: Super Thermal Power Station - FGD Addition
8Project Cost: Rs 900 crore
8Project Description: The developer is scheduled to install an FGD for a 1600 MW (2*800 MW) unit thermal power plant. The company is expected to float tenders for the same. At present, feasibility studies are ongoing. The project is expected to kick off in early 2019. RFQ for supply and installation of FGD are expected to be out by the third quarter of 2018.
8The major requirement will be FGD, stacker and reclaimer, earth work, cranes, pipes, installation, gypsum disposal, wet lime among others.
8Project Event: RFQs for supply and installation of FGD are expected to be out by the Q3 2018.
8Expenditure Approval: Q1:2018
8RFQ Date: Q3:2018
8Release Date: Q4:2018
8Start Date: Q2:2019
8Completion Date: Q1:2022
Click here for more information
8Project Name: Thermal Power Maintenance Project (Unit - 11)
8Project Cost: Rs 12 crore
8Project Description: The owner has planned na 18-day scheduled mini overhaul of the Unit-11 B-TPS (200 MW) in the 1188 MW Thermal Power Plant covering turbine bearings, refilling of gas for HP, IP, LP turbine cylinders, boiler linings, safety valves, nozzles, inspection of rotor blades, relays, fuses, pipes, replacing of conveyor belts, bucker wheel, among others.
8Project Event: RFQ for equipment is expected by Mid-December 2017.
8Expenditure Approval: Q2:2017
8RFQ Date: 17/Dec/2017
8Release Date: Jan/2018
8Start Date: 1/Mar/2018
8Completion Date: 18/Mar/2018
Click here for more information


**********************************