Software updates: Oil and Gas Projects.
Nov 08: 8Project Name: Greenfield 2G Bio-Refinery
8Project Cost: Rs 600 Crore
8Project Description: An existing company along with EPC contractor and licensor, Institute of Chemical Technology, is planning to construct an ethanol plant based on the DBT-ICT 2G Ethanol technology developed indigenously to produce 100KL fuel-grade ethanol per day, primarily from biomass and will use approximately 450 tons of biomass per day at its refinery.
8Project Event: RFQ for long lead items is expected by January 2018.
8Expenditure Approval: Q1:2017
8RFQ Date: Jan/2018
8Release Date: Mar/2018
8Start Date: Q2:2018
8Completion Date: Q1:2021
Click here for more details.
8Project Name: Greenfield LPG Bottling Plant
8Project Cost: Rs 161 Crore
8Project Description: An existing company is planning to set an LPG Bottling Plant with a capacity of 120000 MTPA by installing 3 X 600 MT mounded storage vessels.
8Project Event: RFQ for licensor selection is expected by January 2017.
8Expenditure Approval: Q3:2017
8RFQ Date: Jan/2018
8Release Date: Feb/2018
8Start Date: Q2:2018
8Completion Date: Q2:2020
Click here for more details.
8 Project Name: Oil Field Development Drilling
8Project Cost: Rs 823.30 Crore.
8Project Description: Promoter is planning the development of an existing oil field.The project involves development drilling of 21 wells, one production installation and laying of approximately 90 km of pipelines(50mm to 300 mm dia). Currently, the project is in pre-clearance phase.The TOR for the project is expected by December 2017. Moreover, promoter has also released the tender for EIA studies for the block. The tender is in finalization stage as of now. The process of hiring an EPC contractor for production installation and the pipeline laying is expected to begin soon. RFQ for the rigs, Xmas Trees, Cementing, Wireline, Drill Collar etc is expected shortly.
8Project Event: RFQ for EPC contractor for production installation and the pipeline network is expected by Q1 2018.
RFQ for hiring services for rigs and equipment is expected by Q2 2018.
8Expenditure Approval: Q2/2017.
8RFQ Date: Q1/2018.
8Release Date: Q1/2018
8Start Date: Q4/2018
8Completion Date: Q4/2020
Click here for more details

8 Project Name: DG Set Hiring.
8Project Description: Promoter is planning to hire Diesel Generators (DG Sets) for various ongoing projects. The project involves supply as well as maintenance of Gensets on annual contract basis for an overall period of 3 years. The contractor shall be responsible for the supply of fuel. Further RFQs for the project are expected shortly. 
8Project Event: RFQ for hiring Diesel Gensets are expected by November end 2017.
8Expenditure Approval: Sep/2017
8RFQ Date: 25/Nov/2017
8Release Date: Dec/2017
8Start Date: Feb/2018
8Completion Date: Feb/2021