Nov 08: 8Project Name: Thermal Power Station - Dismantling 8Project Cost: Rs 65 crore 8Project Description: The developer is planning to retire and dismantle Units 1 and 2 (2*120 MW) of it's 870 MW (3*210 + 2*120MW) thermal power plant. At present, the consultant is working on the feasibility study. As of now, these two units have already been shut down since July, 2017 due to low schedule. RFQs for civil work and dismantling services of various equipment are expected by the 1st quarter of 2018. 8The major requirement will be cranes, dozers, dismantling services for electrical, mechanical and control and instrumentation (C&I) equipment, onsite inspection, inventorying, segregation and estimation among others. 8Project Event: RFQ for dismantling services of various equipment is expected by Q1 2018. 8Expenditure Approval: Q3:2017 8RFQ Date: Q1:2018 8Release Date: Q1:2018 8Start Date: Q3:2018 8Completion Date: Q2:2019 Click here for more information